Blue skies, very warm – is it really the very end of September in the UK? I went round to the back of the site where work was going on with what I take will some garden area. Then I could see that an area on the far right which had largely been a storage area was now cleared to give access to the gates at that end. And, presumably to give space for the disassembly of the Cerex crane in a week’s time. The skyline of Harpenden will once again return to normal.
As I went around the interiors, tiles were going down now that the moisture levels had stabilised, and I saw that units for the kitchens were stacked in one room ready for installation and doors were having their hinges added, and a lot of the plastering was drying out. I did find one very strange sight – in one very small area that was being plastered the plasterer was equipped with stilts!
It seemed strange to me that it was the ground floor areas that were so much further ahead than the upper floors. It was not till later I noted that the scaffolding on the cattages at the end had been removed.

No comments:
Post a Comment