Welcome

I am Rod Wynne-Powell, and this is my way to pass on snippets either of a technical nature, or related to what I am currently doing or hope to be doing in the near future.

A third-person description follows:
Professional photographer, Lightroom and Photoshop Workflow trainer, Consultant, digital image retoucher, author, and tech-editor for Martin Evening's many 'Photoshop for Photographers' books.

For over twenty years, Rod has had a client list of large and small companies, which reads like the ‘who’s who’ of the imaging, advertising and software industries. He has a background in Commercial/Industrial Photography, was Sales Manager for a leading London-based colour laboratory and has trained many digital photographers on a one-to-one basis, in the UK and Europe.
Still a pre-release tester for Adobe in the US, for Photoshop, he is also very much involved in the taking of a wide range of photographs, as can be seen in the galleries.

See his broad range of training and creative services, available NOW. Take advantage of them and ensure an unfair advantage over your competitors…


View any Gallery by Clicking the relevant TEXT Headline

Showing posts with label Jarvis. Show all posts
Showing posts with label Jarvis. Show all posts

Saturday, 21 April 2012

Closing Stage of Construction

The atmosphere at the site was somewhat different, people without hard hats scurrying around organising deliveries; new unfamiliar faces of different workers, taking over from those of the main contractors, Jarvis and Toureen Mangan. There was an air of vibrancy, excitement and purpose, it did not seem like just another day, one of many; everyone seemed to know that this chapter was coming to a close and the birth of a new one was just beginning. Foresters was going to become a community of homes and shops, the shells were going to be filled, the sounds would no longer be those of construction, they would be the sounds of ordinary life, of new beginnings.

Although I found that in the retail units there was still work to be done, I realised that progress work was no longer with the main contractors, and that my visits had come to a close. I have felt very much a part of this development, I have been shown friendship and respect, and have always been greeted with cheerful banter, told which was their best side, as they struck poses when I passed by, and in return I have ensured that I took photos that always tried to show them in the best light, and it was flattering to be asked for my business card, so they could see what I had covered. Processes were explained to me; features I might be interested in covering were pointed out. It has been good to see how each trade has taken pride in the work they contributed to the whole.

It is interesting to think back to the earliest progress photos I took, during the construction of part of Imperial College, London – the shots were in black-and-white, the camera was a Sinar 5x4 monorail; everything was shot using a tripod and bulb flash, the numbers of shots was limited and far fewer than now where everything has been hand-held, bar the time lapse series taken of the dismantling of the tower crane. Everything has been in colour, yet ranged from the darkest recesses of the basement to exteriors in the brightest of sun. For the technical, I have used from ISO 5000 down to 100, and speeds from 1/4 second to 1/4000th, and everywhere between! And thoroughly enjoyed every minute of it.

Monday, 16 April 2012

Getting Ever Closer to Completion

Jarvis Foresters, Harpenden – Less of a Building Site

Grass and finished paths makes the whole area look more and more like a completed development, and as I entered there were people looking to deliver some of the incomers’ fittings. The sun was shining brightly on the grass, round the back, blossom was appearing on the shrubs. Almost all the paths are now gravel composite where there was tarmac before, and only a few areas remain to be turfed.

Down below the basement is no longer a storage area, but has yet to be marked out for the parking bays, but the security gates are in place, but not yet motorised. Upstairs floor coverings are down in the communal areas, the lifts have their protective sheeting removed as have the glass panels on the staircases, so the next fortnight or so will soon see tenants moving in, and the sounds of construction will be a distant memory, and a new chapter will begin for the new residents.

Wednesday, 4 April 2012

Jarvis Foresters – Grass Goes Down

I made a point of arriving early in order to catch the laying down of the turves as a continuation of the previous day, but learned that what had been done was all that was being laid this side of Easter, so I have shots of the first laying complete, so having captured that I moved to the basement which is much less crowded, but not yet clear enough to do the marking out of the parking bays, and I suspect the pavers outside will need to be completed so that vehicles can enter the underground car park to remove the remaining stored items.

Above ground the metal frames that render the basement skylights safe are mostly in place, the individual garages now have their up-and-over doors. The staircases in some instances have their glass panels, banisters and skirting, and in places metal trim is being fitted.

Wrought-iron black painted rails are being fixed in place, and now most of the exterior path lighting is in place. In some of the apartments the lifts are now having their protective plastic covering removed, more bathrooms have been tidied. Wooden balustrades have yet to painted or varnished, flat signs and numbers are now up – levels of completion vary across the site, and I have tried to reflect this. Toureen Mangan high viz jackets were very much in the majority with Jarvis and Balgard completing numbers.

It was a bright and buzzing area with evidence of the previous night’s rain glistening in bright sunlight, and it was pleasantly warm.

Monday, 2 April 2012

Jarvis Foresters – Paths and Pavers

Toureen Mangan are once again hard at it laying down the tarmac for the paths, which are due an epoxy bonded gravel top surface eventually, the topsoil is down for the grass turf which is due any day now, possibly going down upon the arrival of the forecast rain later this week.

I arrived somewhat late in the afternoon having been absorbed with other work in the morning and early afternoon. The entrance to the site was having the last of the pavers being laid at the service road end as I made my entrance. At the other end, they were also laying the last few blocks as I left the site; the area I had seen started on my last visit was now complete bar the edges. At the far end to the right one of the drains was being given a thorough check and found to be flowing well.

I managed to capture yet another kitchen being completed, and I was able to take some high-level shots from the balcony. And around the back the garden path was tarmacced, and the turves laid much earlier now looked like a lawn.

This is definitely the countdown. Somehow I need to get down to the show the final turf going down within a couple of days, and by that time the entrance to the underground car park should be clear so that it can be emptied for the various bays can be painted.

Tuesday, 27 March 2012

Foresters Ever Closer to Completion

Toureen Mangan people are more in evidence on the Jarvis development site again, now that soil is going down to add the finishing touches to paths and grassy areas to come. And inside the basement is lessening its grip as a storage area.

Upstairs many of the bathrooms and kitchens have been cleaned up, tiles are up on the walls and down on many of the floors, the staircases are looking far more finished and lighting is going in all the common shared areas, and outside lighting for the pathways are being completed.

My sense of humour baffled one of the men when I asked whether this was the Cameron apartment – he was fitting the number ten to the door with infinite precision! I had had to lean into many of the more finished rooms on my knees as much of the protective coverings were being removed and this led to an amusing encounter where one of the builders noticed I had removed my hard hat, since I was always insistent upon only shooting those properly attired I felt very sheepish, thanked him, and scurried back upstairs to retrieve it – I had needed it off to be able to take one of the shots, and was thus ‘improperly dressed’!

Thursday, 15 March 2012

Foresters – Countdown to Completion

Arriving in Harpenden, I found the traffic much busier than normal, and almost every available parking space occupied or had a car patiently queuing whilst the previous tenant was  gathering their shopping and wits in preparation for their departure. I had already driven around the islands between the High Street and service road, so pulled into the back of the development, hoping I’d be allowed to park on site. Fortunately that permission was granted, which meant I need not panic about Traffic Wardens for a change.

The first sight that greeted me was the power-jetting of the brickwork on the cottages, a sure sign that work is nearing completion. Then I spotted the last roof tiling being done, on the garages towards the front of the site, behind the existing shops.

Topsoil is now appearing around the front, so it will not be long before a new colour appears here – the green of grass; the frontage is beginning to look closer to the brochure picture.

Tuesday, 6 March 2012

Foresters Development – Completion Less Distant

Visiting today showed much more groundworks coming on. Externally, the alterations to the pavements and the cable-laying is close to completion, inside, the Portakabin Site Office has gone, and the roof over the Electricity Sub Station nears completion, and many more external walkways have been screeded. Behind now the gardens are taking shape with the turf settling down.

The boiler room in the basement seems to be close to being finished. Upstairs many of the staircases are having the skirting finished and receiving a coat of paint, and overall much of the finished shapes are becoming apparent, and many more bathrooms are being fitted out.

Overall, the pace of change seems to have moved up a gear.

Thursday, 23 February 2012

Foresters Harpenden, 23rd February


The Foresters Development by Jarvis is certainly looking much closer to completion, and I arrived earlier than usual as I needed to return to base by eleven, and once again I am greeted by sunshine, and for a change the weather is pleasantly warm with just a slight breeze.

Around the back turf is going down and the gardens have much of their plants in, though there are more paths to be completed. Around the front screeding is drying. New garages in the front have tiles being hung, and others have their roofs yet to be completed but the weatherproof membrane is down and the battening is nearing completion.

Some pavers are going down at the back of one of the cottages, and many of the exterior doors are being fitted. Many of the kitchens and bathrooms are coming on apace, laminate flooring is being laid, and one staircase has some glass panelling with bold aluminium fittings up, but with its protective sheeting still in place.

As I left I also captured the newly completed re-arrangement of the service road pavements with its bright ringing of double yellow lines, and I gather there are some six weeks till completion, given favourable weather conditions.

Thursday, 9 February 2012

Jarvis Foresters – Fixtures & Fittings


Visiting the Foresters Development this day was slightly less than straightforward as the approach is beset with bright orange plastic guard rails, and the end of the service road is entirely blocked off. The reason for this is down to the number of essential services that are now being brought to the site, and this has involved considerable disruption to both the road itself and much of the pavement and kerbing. Also additional drainage is being added; whilst I was there a fairly deep hole was being widened to take a large concrete sump.

I had already decided that this visit I was going to be using a wider angle lens to capture some of the kitchens and bathrooms as they took shape, and although I have covered some of the more accessible rooms, the smaller or awkward ones needed me to have a shorter focal length than 24mm. What that meant was that my concentration for this visit was more about the interiors and the fixtures and fittings than the groundworks going on.

One pressure I always face is limiting myself to parking close by and avoiding punitive parking fines, by allocating precisely an hour, including donning my PPE (Personal Protective Equipment) and subsequent disrobing to drive back. There were other parts of the site I would have preferred not to have missed, but I am in the midst of a massive tech-editing job, which has an effect on time available as well. Anyone know where I can lay my hands on a forty-eight hour day?

Friday, 27 January 2012

Jarvis Foresters in Cold January Sunshine


When the bathrooms and kitchens are more finished I will use a wider angle lens, but for the moment, the details of the unfinished work is more important than the overall view, so the less wide the shot is, the larger it appears within the galleries. The electricians and carpenters were hard at it, connecting up and testing the electrical wiring, and hanging doors in the corridors.

The garden areas are now being planted, hopefully allowing them to bed in; I just hope the frost does not kill them all! Most of the last roof structures are now weathertight, these are the garages. Outside the site, work has been carried out in the service road parallel to the High Street; it is largely complete but protected by brightly coloured plastic guardrails, so access along the service road is somewhat restricted till these are fully restored. It was good to see that some effort was being made to clean the wheels of vehicles leaving the development site.

Monday, 16 January 2012

Second 2012 Visit to Foresters

It was a crisp and bright winter’s day and for a change there was not the biting wind that we have had recently, so it did not seem so cold, and as I entered the site there was much more of the intended Retail part of the development to be seen as the scaffolding was now removed completely, and this was an area that I had not covered on my last visit.

There was a lot of outside work being carried out, removing some of the now redundant pipework in one area, and round the back the garden area was being rotivated and receiving topsoil. One of the electricians spotted my capturing his work in the retail section and told me that the main board area was now far advanced, so I shot that and I spotted that doors were now being hung on the storage areas in the basement, and also the water pipework now had meters fitted.

I had no time to visit much of the interiors this visit, except the drywalling was going on in the future retail section, so this will take priority on my next visit.

Wednesday, 14 December 2011

Last 2011 Visit to Foresters

This is likely the last visit in 2011 to the Foresters Development in Harpenden, and there was occasional sunshine, but it had rained a good deal over the last few days, so it was extremely muddy.

I spent some time covering the connection being made to heavy duty three-phase electricity cabling immediately below the Site Office Portakabin. I was intrigued by the clever shear bolts used to ensure a sound electrical connection; the studs shear when the intended torque is reached. The individual phases are shrink-sealed with a semiconductor material to ensure there is no crosstalk between the individual phases, and a conducting shield is then wrapped around the joints and bonded at each end by jubilee clips, before being covered by an outer plastic cover that is itself sealed at each end. The cover has two ports into which a mastic is poured that encases the connections completely weather-sealing them.

Nearby another man is grinding several steel reinforcing rods that were protruding from the edges of the pit where the electrical work was being done.

Elsewhere I took shots that finally showed some of the buildings more clearly now that the scaffolding is down, and that interior finishing was going in, and the work that was nearing completion at the back of the site, on the curving pathway.

Wednesday, 30 November 2011

Jarvis Foresters Exteriors Beginning to Show

Today's visit, again on a sunny day, showed me what had changed in the interim since my last visit. The trench newly dug on my last visit was now being populated with pipework. Many more kitchen and bathroom fittings were going in, and the floor tiles which had been down earlier, were all covered by protective rubber mats.

Windows which had been barely visible behind a lattice work of scaffolding and some deteriorating plastic sheeting were now visible to the world, so the final look of the buildings is becoming more apparent with each visit.




Beyond and to the left of the Site Office Portakabin, the garages now have the roof trusses up, here is one of the few places on site where scaffolding is still visible; the majority being behind the buildings to allow the renderers to work.

Whereas on most previous visits I would move around the various buildings using the outside stairs and ladders, today I did most of walking within the building using concrete stairs, so despite the bitter wind, I traversed the site in comparative comfort.

The unseasonable weather this late autumn is certainly a far cry from the snow that was here this time last year, and is probably very welcome for those still working outside.

Tuesday, 15 November 2011

Foresters Losing the Scaffolding

It is good to see the brickwork more clearly and most of the blind gaps replaced by windows; the building show much more of their finished looks, and now that the render at the back has been completed, they were getting ahead with the same for the top halves of some of the buildings at the front.

On the left of the site a row of garages are nearing completion of the walls, and in the apartments many of the kitchen cabinets are going in and some of the bathroom fittings, elsewhere more of the plasterboarding is also going up, together with more of the wooden staircases.

Externally trenches are now being dug for some of the services, and the basement plumbing is even more apparent. It does not seem long before most areas will be weather-sealed, which will mean many of the workers will be inside carrying out their fitting whilst those outside will be concerned primarily with groundwork activity and very much at the mercy of our famous British Weather.

But just for today, we were treated very well indeed with sunshine the entire time I was on site.

Friday, 4 November 2011

Craneless Foresters

The defining sign of the Foresters Development by Jarvis in Harpenden has been removed, and the void from which it rose to tower over the skyline of Harpenden, has been sealed up. Much of the scaffolding that laced the facades of the buildings, has now been removed, and now glimpses of how this development will look in its completed state are visible. White render is being sprayed and smoothed across parts of its surfaces.

Many of the internal rooms are being plastered and tiled and even fitted out with sanitary ware in the form of showers and baths, where floor tiling has been completed these read are now covered in large rubber mats for their continuing protection, wooden staircases are going in, as are internal doors, and outside at the far end tarmac has now gone down. Though there are still several months till completion, at least from outside the impression of how this enclave will look is becoming apparent, but the basement does give some idea due to what it is storing, just how much has still to be built in to achieve completion.

The work to be done is now far more detailed and time consuming, so progress will seem to slow down, even though this is far from the reality. Out at the back are changes that no casual passers-by will see at all, but it is taking shape.

Wednesday, 2 November 2011

Important Meeting with Jarvis Directors

Having worked hard to create photo reports of progress on the Foresters Development by Jarvis, just off the High Street in Harpenden, the dismantling of the crane gave me the vehicle to transport me, to the offices of the developers. Today, I had an important appointment with the Managing Director, Steve Cook.

I had originally been drawn to the site by the sight of the crane as I approached Harpenden back in November of last year. When I learned of its impending removal, I decided that I would attempt to create a time lapse movie of the work by shooting the dismantling one shot every ten seconds over the six or so hours that it took to be carried out, and compiling them into a movie. I was a time-lapse virgin, but I spoke to colleagues and read various articles and mentioned to the site manager, James Blackie that this was my intention, and he thought it might be a very interesting project, and discussed how the operation was to be planned.

Later when he saw what I had produced, he and several of his colleagues told me that it was a very interesting result and when I asked who I might contact at head office, they gave me their Managing Director’s name and contact number, and Jason said yes, he would try and put in a word for me. I then contacted Steve Cook on the following Monday and today at nine thirty I found myself in his office and soon after, in walked the Marketing Director Geoff Hollis.

Only time will tell whether I have convinced these two of my competence and value, but certainly I felt that the presentation went well, and I sincerely hope that at some date in the future I may be invited to tender for work with the company. Above is a photo of the headquarters building shot just the afternoon before.

Friday, 28 October 2011

Scaffold Comes off at Foresters

After a day of rain, I arrive on site in glorious and warm sunshine, but hey, this is the end of October, and the clocks go back this weekend, Summer is officially over!

Somehow the site is not the same without the crane towering over all the work, where it rose out of the concrete two workers are clearing plugs from the skein of concrete, and the gap will soon disappear it is as if they are working on the crane’s tomb.

Elsewhere on site baths are now in in some of the apartments, kitchen units are in, tiles have been laid, and are now covered in hard-wearing rubber mats to prevent heavy boots from damaging them, and those areas not being worked upon are now locked, soon the work will be mainly confined to the interiors, and fitting out whilst the land outside is cleared and prepared for the final levels.

Possibly because it is school half-term there seem to be fewer tradesmen on site, so presumably dads are taking their kids out to exciting venues elsewhere, and making the most of this surprising good weather.

Sunday, 9 October 2011

Jarvis Foresters 7th October Visit

This day’s visit means the last of the high level view point from the Cerex crane at the Foresters Development by Jarvis Homes, as this coming Wednesday sees the dismantling and removal of the crane which has dominated the Harpenden skyline for  much of this year.

A gentle breeze was what the weather forecasters described, but it still felt slightly more than that when I was close to the cabin height to get the last images of the work from this viewpoint.

There forthcoming departure of the crane has meant considerable change to the far right end of the site, as the earlier wooden gates are open and the future road entrance is now visible. Another change is that a bit more of the scaffolding has been dismantled, giving a much clearer view of the finished result. A wooden staircase has gone in in one of the end cottages.

Although upon my arrival the sun was out, by the time I was concluding the skies were lowering and the clouds looked threatening and few drizzling spots of rain were falling.

Friday, 30 September 2011

Jarvis Foresters, Harpenden, 30th September

Blue skies, very warm – is it really the very end of September in the UK? I went round to the back of the site where work was going on with what I take will some garden area. Then I could see that an area on the far right which had largely been a storage area was now cleared to give access to the gates at that end. And, presumably to give space for the disassembly of the Cerex crane in a week’s time. The skyline of Harpenden will once again return to normal.

As I went around the interiors, tiles were going down now that the moisture levels had stabilised, and I saw that units for the kitchens were stacked in one room ready for installation and doors were having their hinges added, and a lot of the plastering was drying out. I did find one very strange sight – in one very small area that was being plastered the plasterer was equipped with stilts!

It seemed strange to me that it was the ground floor areas that were so much further ahead than the upper floors. It was not till later I noted that the scaffolding on the cattages at the end had been removed.

Saturday, 24 September 2011

Jarvis – Foresters Development – September 23rd Visit

Arriving again with sunshine, I took a look around with slightly less pressure this time, as my car was beyond the reach of Traffic Wardens. Certainly many more areas of the roofs are now clad in tiles, but I mistakenly thought some of the scaffolding might have been coming down to reveal more of exterior of the various buildings. On the right of the site, the Retail area was one that I had not really covered completely on my last visit, so this was my priority.

Speaking to one of the tilers working on the circular section of this roof, he told me he was determined to avoid any step in the cone with his work, unlike the other roof close to the entrance done by a different company. It was good to hear voiced such a sense of pride and determination to do a good job!

This Retail section of the construction, is not as far ahead in terms of the roof as other areas on the site, so I was see ing far more carpentry as it slowly begins to take shape on all the steelwork. The three dormers are nearing completion from tilers and carpenters, but have yet to receive their windows. Down below, window frames are being assembled by their final destinations, still shrouded in their protective polythene sheeting.

Ridge tiles and corner tiles were being cemented, and valleys and dormers were being flashed with lead or zinc, so that the completed areas were becoming weather-resistant. Cabling was going in in many areas, and plastering was being done, and in the basement even fluorescent lighting and signage was in use. Hidden around the back of the site, curved walling was quietly progressing in what is the gloomiest part of the site.

The Cerex crane, which has been the most visible feature of this development, is due for disassembly soon, but has proved so useful it has already had its stay extended.