Welcome

I am Rod Wynne-Powell, and this is my way to pass on snippets either of a technical nature, or related to what I am currently doing or hope to be doing in the near future.

A third-person description follows:
Professional photographer, Lightroom and Photoshop Workflow trainer, Consultant, digital image retoucher, author, and tech-editor for Martin Evening's many 'Photoshop for Photographers' books.

For over twenty years, Rod has had a client list of large and small companies, which reads like the ‘who’s who’ of the imaging, advertising and software industries. He has a background in Commercial/Industrial Photography, was Sales Manager for a leading London-based colour laboratory and has trained many digital photographers on a one-to-one basis, in the UK and Europe.
Still a pre-release tester for Adobe in the US, for Photoshop, he is also very much involved in the taking of a wide range of photographs, as can be seen in the galleries.

See his broad range of training and creative services, available NOW. Take advantage of them and ensure an unfair advantage over your competitors…


View any Gallery by Clicking the relevant TEXT Headline

Showing posts with label James Blackie. Show all posts
Showing posts with label James Blackie. Show all posts

Friday, 10 December 2010

After the Frosts, Concrete Pouring in Harpenden

Thursday was scheduled for the pouring of the concrete for the ground floor at the Jarvis Development in Harpenden, after the hiatus caused by recent unseasonably cold and frosty weather. I made myself known to James Blackie the site Manager and the Project Manager for the sub-contractor.
I arrived too late to catch the first mixer arriving, but not so late as to miss the pouring. There were many more trades on the site this time, and Sean Mooney, the Project Manager for Toureen Mangan (currently the main subcontractor on site) took me to see the extra step he was taking to ensure they could pour with impunity, he had sealed the area beneath with frost blankets and installed Calor gas Space heaters!

It was interesting to see a trident-style mini flame thrower being used to clear some of the snow that had accumulated in some parts of the shuttering, as well as some workmen using magnets to collect stray steel wiring from the same recesses.

The crane was also active transporting beams from their storage area to the next section to be shuttered, and all around were small groups intent on sawing timber, creating new shuttering and vibrating or smoothing out the concrete.

When possible Concrete Mixer lorries were exiting the site as the next was arriving to take its place, but there did seem to be some occasions when traffic delayed their arrival, which was a shame with such a tight schedule due to the cold spell returning soon.

Wednesday, 17 November 2010

Invited Back!

A day after the visit to the new development site in Harpenden, I got a call from the Toureen Project Manager asking would I like to return – another one of those .009 nanosecond hesitation moments before accepting! I gathered the weather was closing in the next day, and as I was all prepared I asked whether I could come over shortly.

This time though the viewpoint was higher, the light was lower, so the shots were less exciting, but they were meaningful as they provided an overview and told me more about what I had shot from outside the day previously. I now understood more of what had been happening at the far side of the site, which had been unclear from my previous viewpoint. These shots completed the story of the previous day. I got to meet two more of the men on site; Bob the Crane Operator and Sean Mooney, Toureen Mangan’s Site Manager, and James Blackie, the Jarvis Site Manager, very kindly took the shot of me part way up the tower crane.

It looks like I’ll be back to tell more of the story of this development. So thanks to all who made this possible.